সিদ্ধিরগঞ্জ ৩৩৫ মেঃওঃ কম্বাইন্ড সাইকেল বিদ্যুৎ কেন্দ্র

Plant Title:
Siddhirganj 335 MW Combined Cycle Power Plant (CCPP)
Plant Location:
Siddhirganj, Narayanganj
Fuel:
Natural Gas
EPC Contract Price:
EURO: 78,652,923 + USD: 196,098,772 + BDT: 2,795,081,706
Financed By:
Govt. of Bangladesh & The World Bank
Total Capacity:
335 MW
EPC Contractor:
JV of Isolux Ingenieria S.A, Spain and Samsung C&T Corporation, Korea
COD of Simple Cycle:
01/05/2018
COD of Combine Cycle:
10/09/2019

Name

GT

Capacity

218 MW

Installation capacity

218 MW

COD

1st  May 2018

Fuel type

Natural Gas

Manufacturar

General Electric, USA

Thermal Efficiency

 

 

Name

ST

Capacity

117 MW

Installation capacity

117 MW

COD

10th September, 2019

Fuel type

-

Manufacturar

General Electric, USA

Thermal Efficiency

54.55%, CC Mode [Thermal efficiency of Combined Cycle]

Executive Agency

Electricity Generation Company of Bangladesh Ltd.

EGCB Cost

48,930.32 Lakh BDT

DPA Cost

294,147.66 Lakh BDT

GOB Cost

54,051.21 Lakh BDT

Total Costs

397,129.19 Lakh BDT

EPC Contract signing date

28-05-2012 

Configuration

1GTG:1 HRSG:1STG

Operation Date

2018-05-05 (Simple Cycle); 2019-09-10 (Combined Cycle)

Capacity

335.4 MW (net)

LTSA

 

Land Lease Agreement with BPDB

July 27, 2011 

Provisional PPA with BPDB

September 16, 2013 

GSA with TGTDCL

August 18,2015

 