সোনাগাজী ৭৫মেঃওঃ সৌর বিদ্যুৎ কেন্দ্র

সোনাগাজী ৭৫মেঃওঃ সৌর বিদ্যুৎ কেন্দ্র, সোনাগাজী, ফেনী

Plant Title:
Sonagazi 75 MW Solar Power Plant

Plant Location:
Purba Borodhali, Charchandia, Sonagazi, Feni

EPC Contract Price:
70 million USD

Financed By:
IDA (World Bank) and GOB.

Total Capacity:
75 MW (Net)

EPC Contractor:
Trina Solar-HYDC JV, China.

Owner’s Engineer:

TUV SUD South Asia and TUV SUD Bangladesh JV

 

 Plant type

Solar Power Plant

Net Capacity

75 MW ac

Installation Capacity

 96.34 MW dc

COD

1st April 2024 (Under declaration)

Renewable Energy Source:

Natural Solar Irradiation

Manufacturer

PV Module: Trina Solar, China

Central Inverter: Sungrow, China

PV Module Efficiency

22% (as per manufacturer’s Data Sheet)

Site Image of Main Installations

 

PV modules and Inverter Stations

Substation

Evacuation Transformers

230KV Control Building

33KV Control Building

230 KV Transmission line (13.33 KM)

Plant Night View

 

Executive Agency

Electricity Generation Company of Bangladesh Ltd. (EGCB)

EGCB Cost

Tk. 62.61 Crore

DPA Cost

Tk. 725.63 Crore

GOB Cost

Tk. 87.54 Crore

Total Costs

Tk.  875.78 Crore

Project Period

July/2019 - June/2024

EPC Contract Signing Date

June 15, 2021

Power Evacuation to Grid

230KV bus at Mirshari 230/33KV Grid Substation, PGCB

Back Feed Date

February 19, 2024

Power Delivered to Grid (First)

February 24, 2024

Dependable Capacity

-

Operation and Maintenance (O&M) Contractor for 3 years

EPC (Trina Solar- HYDC JV, China)

Power Purchase Agreement (PPA)

Under progress